Top Solar Farm Construction Pipelines

Looking to 2023: Top Solar Farm Construction Pipelines

Using the Geospatial Energy and Mining (GEM) project database from BuildCentral, we’re examining the United States’s top solar farm construction pipelines. To do that, we’re taking advantage of GEM’s complete project lifecycle tracking to look exclusively at solar farm projects set to begin construction in 2023.

In doing so, take note of the detailed project reporting that BuildCentral’s 75-plus researchers compile and update daily. For each of the leading states for solar farm construction pipelines, we highlight one sample project report.

Top 2023 Solar Farm Construction Pipelines

Illinois

Tilden Solar Project

Project Type: Solar Farm Construction Type: New
Interconnection: Eastern
Estimated Value: $180 million
Power Output: 150 MW Site Area: 486 hectares
Sector: Private On/Offshore: Onshore
Location: ChesterIL 62233. farmland S of Tilden
Details: Status: Special Use Permit Approval Granted By Zoning Board of Appeals | Method of Appointing Contractor Yet To Be Determined * 150 MW solar farm * Solar photovoltaic panels * Solar mounting & tracking structures * Electrical cabling * Trenching * Grid connection * Inverters * Access roads * Associated site & civil works
Stage: Proposed
Construction Start: 10/2023
Construction End: 9/2024

Minnesota

Red Rock Solar Project

Project Type: Solar Farm Construction Type: New
Interconnection: Eastern
Estimated Value: $86.159 million
Power Output: 60 MW Site Area: 194 hectares
Sector: Private On/Offshore: Onshore
Location: Midway TownshipMN 56159
Details: Status: Certificate of Need (Mpuc Docket No Ip-7014/Cn-19-486) & Site Permit (Mpuc Docket No Ip-7014/Gs-19-620) Approval Granted By Minnesota Public Utilities Commission | Method of Appointing Contractor Yet To Be Determined * 60 MW solar farm * Solar photovoltaic panels * 34.5/161 kV step-up substation * Inverters * Electrical collection & communication lines * Solar mounting & tracking structures * Electrical cabling * Electrical wiring * Transformers * Supervisory Control & Data Acquisition system * Trenching * Grid connection * Transmission grid * Connection to Blue Lake-Wilmarth-Interstate Interconnection 345 kV transmission line * Agricultural woven wire fence (approx 7 ft) * Security fencing around substation (approx 6 ft) * Operation & maintenance building * 10 stormwater drainage basins * 3 weather stations (10 ft) * 3 temporary laydown areas * Security cameras * 6.6 km gravel access roads * Associated site & civil works
Stage: Starts in 4-12 months
Construction Start: 8/2023
Construction End: 8/2024

New York

Greens Corners Solar Project

Project Type: Solar Farm Construction Type: New
Interconnection: Eastern
Estimated Value: > $100 million
Power Output: 120 MW Site Area: 1074.44 hectares
Solar Panel: 460000
Sector: Private On/Offshore: Onshore
Location: WatertownNY 13601. W of Interstate 81, SW city of Watertown
Details: Status: Major Renewable Energy Facility Construction Permit Granted By Office of Renewable Energy Siting | Written Public Comments closed | Public Comment Hearing closed | Grid Connections In Progress With New York Independent System Operator | Method of Appointing Contractor Yet To Be Determined *120 MW solar farm *460,000 Solar photovoltaic panels *Single-axis tracking structures *Inverters (44 units) *Medium voltage collection system *On-site interconnection facility *115 kV transmission line *Step-up transformer *Internal infrastructure *Access roads *Fencing *Temporary laydown areas for equipment staging *Energy storage components *Substation *Associated site & civil works
Stage: Starts in 1-3 months
Construction Start: 1/2023
Construction End: 1/2024

Texas

Flatland Solar Project

Project Type: Solar Farm Construction Type: New
Interconnection: Texas
Estimated Value: > $100 million
Power Output: 180 MW Site Area: 279.23 hectares
Solar Panel: 690000
Sector: Private On/Offshore: Onshore
Location: LubbockTX 79404. 160.93 km S of Lubbock
Details: Status: Enbridge Inc. Acquired Tri Global Energy * 180 MW solar farm * 690,000 solar photovoltaic panels * Solar mounting & tracking structures * Electrical cabling * Trenching * Grid connection * 138 kV interconnection * Associated site & civil works
Stage: Proposed
Construction Start: 8/2023
Construction End: 8/2024

Virginia

360 Solar Center Project

Project Type: Solar Farm Construction Type: New
Interconnection: Eastern
Estimated Value: $25-$100 million Size: 19602000
Power Output: 52 MW Site Area: 323.74 hectares
Solar Panel: 120000
Sector: Private On/Offshore: Onshore
Location: SkinquarterVA 23120
Details: Status: Conditional Use Permit Application Submitted To Chesterfield County | Power Purchase Agreement Signed With Dominion Energy | Notice of Intent To File Permit By Rule Application Submitted To Virginia Department of Environmental Quality | Method Of Appointing Contractor Yet To Be Determined *52 MW solar farm *120,000 Solar photovoltaic panels *Solar mounting & tracking structures *Electrical cabling *Trenching *Grid connection *Stormwater Management *Associated site & civil works
Stage: Starts in 1-3 months
Construction Start: 2/2023

Want to learn more about GEM?

If you found this blog informative and are curious about using GEM, or just getting more information, reach out to us here! We’re looking forward to hearing from you. In the meantime, feel free to sign up for our newly released GEM Newsletter as well.

Leave a Reply

Your email address will not be published. Required fields are marked *